It is raining yet again, so instead of installing the exterior siding and front porch columns I will post the weekly update.
We finally got the framing finished, got the house weather proofed, completed HVAC and plumbing, and started wiring.
We are currently about 10 days behind schedule due to weather delays, but should be able to make some of that back up.
First update is on the framing of the basement.
When we designed the house, we didn't know exactly where the slope of the lot would be, and I was pleased to find out we had room to add another window to the basement to help bring in more light to the rec room/bar area.
Here is a picture of the basement framed per the original plan

And here it is after we added a new window.

This picture is taken in the rec room area looking towards the HT entrance. The bar is on the right next to the stairs.

This is looking at the front wall of the HT.

This is the opening for the equipment rack. The rack is recessed into a mechanical closet that will also be lined with DD & GG.

We then completed the underframing for the poured concrete stoop that acts as the ceiling of the safe room.


This is what it looks like from inside the safe room.

Next, the concrete porch was poured.

And the house is completely weather proofed.

I will post pictures of the mechanical work as well as an updated schedule in following posts.
We finally got the framing finished, got the house weather proofed, completed HVAC and plumbing, and started wiring.
We are currently about 10 days behind schedule due to weather delays, but should be able to make some of that back up.
First update is on the framing of the basement.
When we designed the house, we didn't know exactly where the slope of the lot would be, and I was pleased to find out we had room to add another window to the basement to help bring in more light to the rec room/bar area.
Here is a picture of the basement framed per the original plan

And here it is after we added a new window.

This picture is taken in the rec room area looking towards the HT entrance. The bar is on the right next to the stairs.

This is looking at the front wall of the HT.

This is the opening for the equipment rack. The rack is recessed into a mechanical closet that will also be lined with DD & GG.

We then completed the underframing for the poured concrete stoop that acts as the ceiling of the safe room.


This is what it looks like from inside the safe room.

Next, the concrete porch was poured.

And the house is completely weather proofed.

I will post pictures of the mechanical work as well as an updated schedule in following posts.

























































