I've always wanted a room that was purposed for HT, inwall wiring etc. After years of wanting and a few of planning, I have finally started my build. This has been a slow process, I actually started Sept. 08 when I bought my first ten 2 x 4's.
Certainly not on the grand scale as many builds here but, a true DIY effort. I didn't have a lump sum budget and have been spending on average about $75/month on materials and tools. The theater is 12'-3" wide by 22' long with an 8 foot tray ceiling and 7" soffits. It will initially be a 7.2 surround set up but also wired for 9.2.
The room is finally reaching a point were it is worth showing. Here are some current pictures of the stairs and back wall.



I'm working my way around the room and have been struggling on a decision about were to place the larger of two subwoofers. It measures about 26" deep by 24" tall and 24" wide. I'm hoping to install it recessed in the front wall were the fireplace jog is. Here is an image of what I'm thinking. Im open to suggestions on the best way to do this.

The plan right now is to install additional lighting, finish the A/V and network wiring, HVAC and have the sheetrock completed by January 1, 2010
Certainly not on the grand scale as many builds here but, a true DIY effort. I didn't have a lump sum budget and have been spending on average about $75/month on materials and tools. The theater is 12'-3" wide by 22' long with an 8 foot tray ceiling and 7" soffits. It will initially be a 7.2 surround set up but also wired for 9.2.
The room is finally reaching a point were it is worth showing. Here are some current pictures of the stairs and back wall.



I'm working my way around the room and have been struggling on a decision about were to place the larger of two subwoofers. It measures about 26" deep by 24" tall and 24" wide. I'm hoping to install it recessed in the front wall were the fireplace jog is. Here is an image of what I'm thinking. Im open to suggestions on the best way to do this.

The plan right now is to install additional lighting, finish the A/V and network wiring, HVAC and have the sheetrock completed by January 1, 2010



































