Quote:
Originally Posted by Larry M 
No picture updates but Saturday was a nice progress day
I wrapped up the plumbing and electrical is 98% roughed in. Just need to fix up the switch boxes and run 14-3 instead of 14-2 to the switched outlet for the star ceiling outlet (wasn't thinking straight). I also called the town inspectors and Thursday the plumbing inspector is coming and Friday electrical inspector will come.
Also spoke to both Cablevision and Fios and both are sending technicians this week to fix the cable issues Dennis and I have been talking about. Dennis a big thank you for motivating me to call them. I was very nice to them on the phone and told them I just want it done right and they both agreed to come this week and fix the issue. I didn't ask for compensation or mention I would cut the wires so I am putting faith in them to do what is right.
If all goes well I will schedule framing inspection for next week and start hanging OSB. Now that I am to this stage, what do I need to get into my walls before it is locked down?
Besides:
audio cables to speaker locations
CAT5 to network locations and projector
Coax cable to possible future sub locations
What else should I run?
Should I do long HDMI runs to the projector? Or go with something like this? Monoprice Extender
I don't want to close up the walls and say oh crap

No picture updates but Saturday was a nice progress day
I wrapped up the plumbing and electrical is 98% roughed in. Just need to fix up the switch boxes and run 14-3 instead of 14-2 to the switched outlet for the star ceiling outlet (wasn't thinking straight). I also called the town inspectors and Thursday the plumbing inspector is coming and Friday electrical inspector will come.
Also spoke to both Cablevision and Fios and both are sending technicians this week to fix the cable issues Dennis and I have been talking about. Dennis a big thank you for motivating me to call them. I was very nice to them on the phone and told them I just want it done right and they both agreed to come this week and fix the issue. I didn't ask for compensation or mention I would cut the wires so I am putting faith in them to do what is right.
If all goes well I will schedule framing inspection for next week and start hanging OSB. Now that I am to this stage, what do I need to get into my walls before it is locked down?
Besides:
audio cables to speaker locations
CAT5 to network locations and projector
Coax cable to possible future sub locations
What else should I run?
Should I do long HDMI runs to the projector? Or go with something like this? Monoprice Extender
I don't want to close up the walls and say oh crap
We just finished up the low voltage runs...I ran a 50 ft. HDMI cable from Blue Jeans. But I also ran 6 Cat wires to the projector area which would allow for HDMI baluns if needed. And we also ran a two inch conduit from the projector to the rack area. That would be a relatively easy way for you to future-proof.
























































































