BeerParty, I've been working on just that.

Not too much progress, but I have been widdling away at a few things.
I've now got the following electric circuits wired and operating:
-Dedicated 15amp to the projector
-Dedicated 20amp to three different subwoofer outlets. (one in the front of the room, and one to each rear corner, this should give flexibility in placement)
- Two Dedicated 20amp to the equipment rack location.
-lighting runs (riser step lights, 6 sconces) are now wired to the switch location (which will likely be Lutron Spacer). (I've got to run rope lights and screen cans back to switch, but those will be run in the soffits once built)
So you can see, I'm starting to fill up that new panel!
BTW, there's not a chance in the world that I would stop watching movies during construction. This stratagy IS slowing me down, but we're enjoying the heck out of the room the whole time.
Next up, installing can lights above the bar and screen. Installing hvac registers and return. Then sheetrock the ceiling.